PMI-RMP Stakeholder Engagement Practice Question
Two project stakeholders disagree on the severity of a risk, leading to an impasse. What is the best way to resolve this?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Facilitate a structured assessment session using established qualitative or quantitative criteria.
Using objective, data-driven assessment criteria helps move from subjective opinion to logical agreement.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Facilitate a structured assessment session using established qualitative or quantitative criteria.
Why this is correct
Objective criteria provide a neutral basis for consensus.
- ✗
Assign the highest severity level to be safe.
Why it's wrong here
Over-estimating risks can lead to unnecessary resource allocation.
- ✗
Flip a coin to determine which severity level to use.
Why it's wrong here
This is unprofessional and ignores the importance of risk assessment.
- ✗
Agree with the stakeholder who has more seniority.
Why it's wrong here
Seniority does not necessarily equate to accurate risk assessment.
Visual reference
About these practice questions
One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.