PMI-RMP Risk Process Facilitation Practice Question
If a qualitative risk analysis is showing inconsistent results, what should you review first?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Risk Management Plan's definitions of probability and impact
Inconsistent results often stem from poorly defined risk definitions or subjective interpretations of the probability and impact scales.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The project charter
Why it's wrong here
The charter doesn't define risk scales.
- ✓
The Risk Management Plan's definitions of probability and impact
Why this is correct
Clear definitions are required to ensure consistency in assessment.
- ✗
The risk register
Why it's wrong here
The register shows the results, not the cause of the inconsistency.
- ✗
The project budget
Why it's wrong here
The budget doesn't affect risk assessment methodology.
About these practice questions
One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.