People — Leading Projects
hard
Based on the exhibit, what is the MOST likely cause of the resource issue?
Exhibit
Refer to the exhibit. ``` Resource Name: John Doe Role: Senior Developer Allocation: 100% (40 hrs/week) to Project Alpha Actual Hours (last 2 weeks): 55 hrs/week Project Health: On schedule, but developer reports burnout ```