A program manager is leading a program to enhance cybersecurity resilience across a global enterprise. The benefits realization plan includes a benefit of 'reduced number of security breaches by 50% within 18 months.' Six months into the program, the program manager notices that one project is implementing a tool that will reduce breaches but also increase network latency, potentially impacting another benefit of 'improved system performance.' What should the program manager do?
This is correct because benefits management involves managing interdependencies and trade-offs. The program manager must evaluate the impact of the tool on both benefits and make informed decisions. Adjusting the plan ensures that the overall benefit optimization is achieved. This aligns with PgMP's focus on balancing competing benefits and maintaining alignment with strategic objectives.
Why this answer
The program manager should assess the trade-off between the two benefits and adjust the benefits realization plan to balance the impacts. This involves analyzing the impact of the security tool on system performance and considering mitigation strategies. Managing benefit interdependencies is a key responsibility in program benefits management, ensuring that overall program value is optimized.
Exam trap
The trap here is assuming that one benefit always outweighs another or that escalation is the first step without analysis.