76
MCQmedium

During program planning, which plan is used to ensure that the program stays within its budget?

A.Project Budget Plan.
B.Program Roadmap.
C.Financial Management Plan.
D.Governance Plan.
AnswerC

The financial plan covers the entire program's budget.

Why this answer

The Financial Management Plan describes how program finances are planned, managed, and controlled.

77
Multi-Selectmedium

Which TWO of the following should be included in a program communication plan?

Select 2 answers
A.Detailed technical design specs for each project.
B.The salary information for all program staff.
C.Identification of stakeholder communication needs.
D.The personal email addresses of all stakeholders.
E.The delivery methods for communication.
AnswersC, E

This is the basis of the plan.

Why this answer

A communication plan ensures the right information goes to the right people at the right time. Stakeholder needs and delivery channels are critical components.

78
MCQhard

A program manager discovers that a project manager is not following the program's reporting standards. What is the best course of action?

A.Provide training and mentoring on the program standards.
B.Take over the project manager's reporting responsibilities.
C.Remove the project from the program.
D.Report the project manager to HR for non-compliance.
AnswerA

Coaching is the first step to correcting performance.

Why this answer

The program manager must coach the project manager and ensure compliance with program standards to maintain data integrity.

79
MCQmedium

How do you manage risks that are common to multiple projects within a program?

A.Assign them to the most senior project manager.
B.Ignore them until they impact a project.
C.Manage them at the program level as shared risks.
D.Manage them individually in each project.
AnswerC

Managing shared risks centrally is a core program management competency.

Why this answer

Common risks should be managed at the program level to ensure a consistent approach and resource allocation.

80
Multi-Selecthard

Which THREE of the following are key components of the Program Governance framework?

Select 3 answers
A.Personal social media policies.
B.Decision-making structures.
C.Procedures for issue escalation.
D.The lunch schedule for the office.
E.Program policies.
AnswersB, C, E

Defines who makes decisions.

Why this answer

Governance frameworks include decision-making structures, policies, and procedures.

81
MCQmedium

During program execution, a major regulatory change impacts the program. Who is responsible for assessing the impact on the benefits realization?

A.The Program Governance Board.
B.The Program Manager.
C.The project managers of the affected projects.
D.The Program Sponsor.
AnswerB

Assessment of the overall program benefits is a core program management duty.

Why this answer

The program manager is responsible for monitoring the environment and assessing impacts to the program's benefits.

82
Multi-Selectmedium

Which TWO of the following are primary components of a Program Management Plan?

Select 2 answers
A.Benefits Realization Plan
B.Technical Design Documents
C.Governance Plan
D.Employee Performance Reviews
E.Individual Project Timesheets
AnswersA, C

Essential for tracking program benefits.

Why this answer

The program management plan is an umbrella document that includes several subsidiary plans, such as the Governance Plan and the Benefits Realization Plan.

83
MCQmedium

A program manager is setting up the program governance structure. Which group is responsible for providing high-level guidance and oversight?

A.Program Management Office (PMO) staff.
B.Program Steering Committee.
C.Project managers.
D.Subject Matter Experts (SMEs).
AnswerB

This group oversees the program's strategic direction.

Why this answer

The Program Steering Committee (or Program Board) provides the oversight and guidance required for program success.

84
MCQeasy

Which of the following is an example of an 'organizational process asset' used in program management?

A.The market price of raw materials.
B.A standard template for a project charter.
C.The team's personality types.
D.The current interest rates.
AnswerB

Templates are common process assets.

Why this answer

Organizational process assets are the plans, processes, policies, and knowledge bases specific to the organization.

85
MCQmedium

When establishing the Program Management Office (PMO), what is the most important factor for success?

A.Aligning the PMO functions with the organizational and program requirements.
B.Using only off-the-shelf software tools.
C.Ensuring the PMO has a large budget.
D.Hiring external consultants.
AnswerA

Alignment is critical for the PMO to provide value.

Why this answer

The PMO must be aligned with the organizational strategy and the specific needs of the program to be effective.

86
Multi-Selecthard

Which THREE of the following are standard ways to manage changes at the program level?

Select 3 answers
A.Formal change request process.
B.Approval from the Governance Board.
C.Ignoring changes to keep the plan simple.
D.Impact analysis of the requested change.
E.Letting project managers approve all changes.
AnswersA, B, D

Required for tracking and approval.

Why this answer

Program change management involves identifying, evaluating, and approving changes through a structured governance process.

87
Multi-Selecteasy

Which TWO of the following are key inputs to Program Formulation?

Select 2 answers
A.Strategic Plan
B.Project status reports
C.Lessons learned from a past project
D.Business Case
E.Detailed project budget
AnswersA, D

The program must align with the organization's strategic plan.

Why this answer

Formulation requires understanding the organization's strategic direction and business needs.

← PreviousPage 2 of 2 · 87 questions total

Ready to test yourself?

Try a timed practice session using only Program Life Cycle Management questions.