Overview of PRINCE2 and Principles
hard
A project manager is leading a PRINCE2 project to develop a new software application. The project board has defined tolerances for time, cost, and scope. During a stage, the project manager forecasts that the stage will exceed its time tolerance by two days. According to the PRINCE2 principle 'manage by exception', what should the project manager do?