Courseiva

MB-330 Practice Question: Implement Warehouse and Transportation Management

A company is implementing outbound processing in Dynamics 365 Supply Chain Management. They want to use wave templates to automate the release of sales orders to the warehouse. The warehouse manager requires that the wave template automatically creates work for picking and then immediately processes the work to generate picking lists. Which two wave template methods should be included in the wave template to achieve this? (Choose two.)

⚠ Common exam trap

The trap here is assuming that allocation or replenishment automatically creates and processes picking work, when in fact those are separate steps handled by different wave template methods.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Process work

To automatically create work and then immediately process it, the wave template must include both the Create work and Process work methods. Create work generates the picking work for the released sales order lines, and Process work then processes that work to make it available for picking. Other methods like Allocate and Replenish serve different purposes and are not required for this specific automation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Process work

    Why this is correct

    The Process work method is necessary to automatically process the created work and generate picking lists. Without it, work would remain in an open status and would not be ready for picking. This method ensures that the work is released for execution on the mobile device.

  • ✗

    Replenish

    Why it's wrong here

    Replenish is used to move inventory from a bulk location to a picking location when there is insufficient quantity. It does not create picking work for outbound orders. The scenario does not mention replenishment needs, so this method is not required.

  • ✗

    Process wave

    Why it's wrong here

    Process wave is not a standard wave template method. Wave templates consist of methods like Create work, Allocate, Replenish, and Containerize. Processing the wave is an action performed after the wave is created, not a method within the template itself.

  • ✓

    Create work

    Why this is correct

    The Create work method is required to generate picking work for the released sales order lines. Without it, the wave would not create any work, and no picking activities could be performed. This method is a fundamental step in the outbound wave process.

  • ✗

    Allocate

    Why it's wrong here

    Allocate is used to reserve inventory for the sales order lines. While allocation is important, it does not create picking work. The scenario specifically requires work creation and immediate processing of that work, which are handled by other methods.

About these practice questions

Courseiva writes every MB-330 question from scratch — 183 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Microsoft exam blueprint

This MB-330 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-330 exam.