Courseiva
Design and implement build and release pipelineshardMultiple ChoiceObjective-mapped

AZ-400 Practice Question: Design and implement build and release pipelines

You are designing a release pipeline that deploys to multiple environments (dev, test, prod) sequentially. You need to require manual approval before deploying to prod. The approver should be able to review the changes and approve or reject. Which feature should you use?

⚠ Common exam trap

Candidates may mistake 'Approval gates' for a valid feature, but Azure DevOps only supports 'approvals' and 'gates' as separate features. Manual approval is achieved via pre-deployment approvers under 'Pre-deployment conditions', not via gates, which are automated checks.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Pre-deployment conditions.

In Azure DevOps release pipelines, to require manual approval before deploying to a specific stage, you configure the pre-deployment conditions of that stage, specifically assigning pre-deployment approvers. These approvers can review the changes and then approve or reject the deployment. This satisfies the requirement directly.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Pre-deployment conditions.

    Why this is correct

    Pre-deployment conditions in Azure Pipelines include artifact filters, schedule times, and pre-deployment approvals, but the approval itself is a separate gate that must be explicitly configured. Merely having pre-deployment conditions does not implement a manual approval workflow by default; it only defines when and under what circumstances the deployment is triggered.

  • Environment checks.

    Why it's wrong here

    Environment checks are automated pre-deployment gates (for example, Azure Monitor, ServiceNow, or custom checks) that validate subscription health, resource readiness, or compliance before a deployment starts. They do not provide a manual user approval with explicit review and reject actions, so they are not the correct mechanism for human sign-off.

  • Approval gates.

    Why it's wrong here

    Approval gates in Azure Pipelines require designated users or groups to explicitly approve or reject a deployment before it proceeds, providing a formal manual sign-off workflow. The gate blocks deployment until an approver responds and supports parallel approvals, reassignment, and commenting for auditability. This is exactly the feature needed for a manual release approval scenario.

  • Manual intervention task.

    Why it's wrong here

    The Manual Intervention task pauses the pipeline execution and waits for a user to resume or stop, but it does not capture an explicit approval decision like an approval gate. It lacks the built-in approval audit trail and approver identity tracking, so it is unsuitable for a formal approval workflow that requires documented review and reject actions.

Visual reference

Client DHCP Server 1 Discover (broadcast) 2 Offer (IP: 192.168.1.10) 3 Request (I accept) 4 Acknowledge (lease confirmed) DORA — the four-step DHCP lease process

About these practice questions

This AZ-400 question is part of Courseiva's 823-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This AZ-400 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the AZ-400 exam.