CTFL-v4 Static Testing Practice Question
What is the primary goal of the 'Rework' phase in a formal review process?
⚠ Common exam trap
Candidates often confuse 'Rework' with 'Follow-up'. Rework is the action taken by the author to fix the identified defects, whereas Follow-up is the verification that those fixes were actually implemented correctly.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To correct identified defects and improve the work product.
The rework phase is dedicated to addressing the defects identified during the review. The author modifies the work product to correct the errors, incorporate suggestions, or clarify ambiguities based on the findings documented by the scribe. This ensures that the final artifact meets the quality requirements and is ready for the next stage of development, thereby preventing the defects from propagating further into the lifecycle.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To verify that the reviewers have understood the author's intent.
Why it's wrong here
Verification of reviewer understanding happens during the review meeting itself, through discussion and clarification. Rework is strictly about the author applying changes to the artifact based on the documented findings, not about checking the reviewers' comprehension of the original document.
- ✓
To correct identified defects and improve the work product.
Why this is correct
Rework is the action taken by the author to rectify the defects flagged during the review. This is essential to ensure that the work product complies with the defined standards and requirements, ultimately improving the final quality of the output before it is used for subsequent phases.
- ✗
To conduct a final assessment of the review's overall cost and time.
Why it's wrong here
Analyzing the review's cost and time is a management activity that occurs after the review process is completed. It is not part of the rework phase, which is focused on technical corrections to the work product itself by the author.
- ✗
To finalize the project plan based on the findings.
Why it's wrong here
Rework is focused on the specific artifact under review, not the overall project plan. While findings might necessitate schedule adjustments, the primary goal of the rework phase is the technical improvement of the artifact, not administrative planning or project management.
About these practice questions
This CTFL-v4 question is part of Courseiva's 144-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official ISTQB exam blueprint
This CTFL-v4 practice question is part of Courseiva's free ISTQB certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CTFL-v4 exam.