ISC Contingency Management Practice Question
Which of the following is the most effective method for testing the efficacy of a Business Continuity Plan without disrupting production operations?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Tabletop exercise.
A tabletop exercise is a discussion-based simulation that tests plan logic and communication without affecting production systems.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Parallel processing test.
Why it's wrong here
Parallel testing requires running both systems simultaneously, which is resource-intensive and disruptive.
- ✗
Cutover test.
Why it's wrong here
A cutover test causes actual downtime for the production system.
- ✗
Full-scale simulation.
Why it's wrong here
Full-scale simulations are disruptive and affect production.
- ✓
Tabletop exercise.
Why this is correct
Tabletop exercises are designed to test decision-making and logic without requiring downtime.
About these practice questions
This ISC question is part of Courseiva's 219-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official (ISC)² exam blueprint
This ISC practice question is part of Courseiva's free (ISC)² certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the ISC exam.