An ISSMP is reviewing an organizational risk register. Which field is essential for effective risk prioritization?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Inherent risk rating

Risk Rating (often Impact x Likelihood) is necessary to rank risks for treatment.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Name of the auditor

    Why it's wrong here

    Not relevant to risk evaluation.

  • Asset owner's email address

    Why it's wrong here

    Administrative detail, not for prioritization.

  • Inherent risk rating

    Why this is correct

    The rating allows for comparative prioritization of threats.

  • Last modified date

    Why it's wrong here

    Administrative metadata.

About these practice questions

One of 219 original ISC practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official (ISC)² exam blueprint

This ISC practice question is part of Courseiva's free (ISC)² certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the ISC exam.