Drag and drop the steps for performing a cloud migration using the 'lift and shift' strategy into the correct order.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Assess current environment, set up target cloud environment, replicate applications and data, transfer data, test and cut over
First assess, then set up target, replicate, transfer data, and finally test and cut over.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Assess current environment, set up target cloud environment, replicate applications and data, transfer data, test and cut over
Why this is correct
This is the correct order because the lift and shift strategy requires first understanding the current environment, then preparing the target, replicating the applications and data, transferring data, and finally testing before cutting over to ensure minimal disruption.
- ✗
Set up target cloud environment, assess current environment, replicate applications and data, transfer data, test and cut over
Why it's wrong here
This is incorrect because the target environment should be set up after assessing the current environment to ensure it meets the requirements; setting up first may lead to misconfiguration.
- ✗
Assess current environment, replicate applications and data, transfer data, set up target cloud environment, test and cut over
Why it's wrong here
This is incorrect because the target environment must be set up before replicating and transferring data; otherwise, there is no destination for the data.
- ✗
Assess current environment, set up target cloud environment, transfer data, replicate applications and data, test and cut over
Why it's wrong here
This is incorrect because replication should occur before the final data transfer to ensure consistency; transferring data first may result in incomplete or out-of-sync data.
Go deeper
Related to this question
About these practice questions
Courseiva writes every CCSP question from scratch — 964 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CCSP practice question is part of Courseiva's free ISC2 certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CCSP exam.