Courseiva

ISC2 CC Business Continuity, DR & Incident Response Practice Question

Which metric defines the maximum acceptable amount of data loss measured in time?

⚠ Common exam trap

ISC2 often tests the distinction between RPO and RTO, where candidates confuse 'data loss' (RPO) with 'downtime' (RTO); the trap is that both are time-based metrics, but RPO is about how far back in time you can recover data, while RTO is about how long it takes to restore service.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Recovery Point Objective (RPO)

The Recovery Point Objective (RPO) defines the maximum acceptable amount of data loss measured in time, typically expressed in seconds, minutes, or hours. It represents the age of the most recent backup or replicated data that must be available to resume operations after a disaster, directly determining the frequency of backups or replication intervals.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Recovery Point Objective (RPO)

    Why this is correct

    Recovery Point Objective (RPO) specifies the maximum tolerable data loss expressed as elapsed time before an incident, directly satisfying the stem's requirement for a time-measured loss threshold. It determines backup frequency, unlike Recovery Time Objective, which bounds service restoration duration instead.

  • ✗

    Mean Time Between Failures (MTBF)

    Why it's wrong here

    MTBF measures average elapsed time between hardware or component failures, so it quantifies reliability rather than tolerable data loss. It is tempting because both metrics are expressed in time units, but MTBF supports availability planning and maintenance scheduling, not the recovery point objective that defines acceptable data loss.

  • ✗

    Mean Time to Repair (MTTR)

    Why it's wrong here

    MTTR measures the average time taken to restore a failed component, addressing availability and recovery speed. Recovery Point Objective (RPO) defines the maximum tolerable data loss measured in time, which is the metric the question describes.

  • ✗

    Recovery Time Objective (RTO)

    Why it's wrong here

    RTO defines the maximum acceptable time to restore service after disruption, not the tolerable data loss window. It is tempting because both are recovery metrics expressed in time, but RTO governs downtime duration, whereas the recovery point objective governs how much data may be lost.

About these practice questions

Courseiva writes every CC question from scratch — 989 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CC practice question is part of Courseiva's free ISC2 certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CC exam.