Courseiva
Business Continuity, DR & Incident ResponseeasyMultiple ChoiceObjective-mapped

ISC2 CC Business Continuity, DR & Incident Response Practice Question

During a disaster recovery test, the team discovers that the backup generator fails to start. What is the BEST immediate action?

⚠ Common exam trap

ISC2 often tests the misconception that any hardware failure during a DR test automatically invalidates the entire test, tempting candidates to choose 'Cancel the test' (Option B) instead of recognizing that documentation and continuation preserve the test's value for other critical components.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Document the issue and proceed

The immediate priority during a disaster recovery test is to document the failure and continue the test to evaluate the remaining components of the DR plan. The backup generator failure is a specific issue that should be logged for post-test remediation, but aborting the test prematurely would lose valuable data on other failover mechanisms, such as UPS runtime, network redundancy, or application recovery. Proceeding with documentation ensures the test's integrity while capturing the incident for root cause analysis.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continue the test with manual procedures

    Why it's wrong here

    While possible, it is better to document the failure first.

  • Cancel the test

    Why it's wrong here

    Canceling loses the opportunity to test other components.

  • Document the issue and proceed

    Why this is correct

    During a disaster recovery test, the immediate priority is to comprehensively identify all weaknesses within the recovery plan, not to fix issues as they arise. Documenting the generator failure and continuing the test allows the team to uncover further potential problems downstream that might be masked or missed if the test were halted. This approach ensures a complete assessment of the entire disaster recovery process, satisfying the diagnostic objective of a test scenario.

  • Shut down the data center

    Why it's wrong here

    Shutting down is unnecessary and could cause more disruption.

About these practice questions

Courseiva writes every CC question from scratch — 976 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CC practice question is part of Courseiva's free ISC2 certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CC exam.