An organization's BIA determines that the payroll system has a Maximum Tolerable Downtime (MTD) of 4 hours. The current recovery plan has an RTO of 2 hours and an RPO of 1 hour. What is the maximum Work Recovery Time (WRT) allowed to meet the MTD?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

2 hours

MTD = RTO + WRT. Given MTD=4, RTO=2, so WRT ≤ 2 hours.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 2 hours

    Why this is correct

    MTD = RTO + WRT → 4 = 2 + WRT → WRT = 2 hours.

  • 3 hours

    Why it's wrong here

    That would exceed MTD.

  • 4 hours

    Why it's wrong here

    That would exceed MTD.

  • 1 hour

    Why it's wrong here

    WRT must be 2 hours or less to meet MTD.

About these practice questions

This CC question is part of Courseiva's 976-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CC practice question is part of Courseiva's free ISC2 certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CC exam.