Courseiva

ISC2 CC Practice Question: Business Continuity, Disaster Recovery, and Incident Response

After a ransomware attack, the IT team restores systems from backups. The CEO asks how quickly data can be recovered. Which metric addresses the acceptable amount of data loss?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Recovery Point Objective (RPO)

RPO defines the maximum acceptable data loss measured in time.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Work Recovery Time (WRT)

    Why it's wrong here

    WRT is time to return to normal operations after systems are restored.

  • Recovery Time Objective (RTO)

    Why it's wrong here

    RTO is time to restore functionality, not data loss.

  • Maximum Tolerable Downtime (MTD)

    Why it's wrong here

    MTD is total acceptable downtime, including recovery and work recovery.

  • Recovery Point Objective (RPO)

    Why this is correct

    RPO defines maximum data loss (e.g., last backup).

About these practice questions

Courseiva writes every CC question from scratch — 976 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CC practice question is part of Courseiva's free ISC2 certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CC exam.