Courseiva
Security Principles →mediumMultiple Choice

ISC2 CC Security Principles Practice Question

A security team identifies a vulnerability in a web application that could allow attackers to steal customer data. The team decides to accept the risk because the cost to fix exceeds the potential loss. This is an example of:

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Risk acceptance

Risk acceptance means acknowledging the risk and choosing not to mitigate it, often due to cost-benefit analysis.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Risk transfer

    Why it's wrong here

    Transferring risk means shifting the financial consequence to a third party, typically via cyber-insurance or an outsourced contract. Here the team retains the loss itself, having judged remediation costlier than the potential impact, which is acceptance. Transfer would be correct if an insurer or partner agreed to bear the loss.

  • ✗

    Risk avoidance

    Why it's wrong here

    Avoidance eliminates the activity or asset generating the risk entirely, such as decommissioning the vulnerable application. This team keeps the application running and simply tolerates the exposure, which is acceptance. Avoidance would be correct if the business could abandon the web application outright.

  • ✓

    Risk acceptance

    Why this is correct

    Accepting the risk means the organisation acknowledges the vulnerability but chooses to tolerate it because remediation costs outweigh the potential financial loss. This deliberate decision to absorb the residual risk, rather than mitigate, transfer or avoid it, is the defining characteristic of risk acceptance within the risk management process.

  • ✗

    Risk mitigation

    Why it's wrong here

    Mitigation applies a control that lowers the likelihood or impact, such as patching or a WAF rule. The team here applies no control and consciously retains the exposure because remediation costs exceed expected loss, which is acceptance. Mitigation would be correct if they deployed a compensating safeguard.

About these practice questions

This CC question is part of Courseiva's 989-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CC practice question is part of Courseiva's free ISC2 certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CC exam.