Courseiva

ISC2 CC Business Continuity, DR & Incident Response Practice Question

A company's BCP requires that critical systems be restored within 2 hours of disruption. Which metric defines this?

⚠ Common exam trap

ISC2 often tests the distinction between RTO and RPO, where candidates confuse the time to restore service (RTO) with the acceptable data loss window (RPO).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Recovery Time Objective (RTO)

The Recovery Time Objective (RTO) defines the maximum acceptable time that a system or application can be unavailable after a disruption. In this scenario, the requirement to restore critical systems within 2 hours directly specifies the RTO. It is a key metric in business continuity planning that drives the design of failover and recovery strategies.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Mean Time to Repair (MTTR)

    Why it's wrong here

    MTTR measures the average time taken to repair a failed component once work begins, not the maximum tolerable downtime after disruption. It is tempting because both concern repair duration, but the BCP's two-hour target is a Recovery Time Objective (RTO), an agreed maximum for restoring service.

  • ✓

    Recovery Time Objective (RTO)

    Why this is correct

    Recovery Time Objective defines the maximum acceptable time to restore a system after disruption. A two-hour restoration requirement is therefore an RTO, distinguishing it from Recovery Point Objective, which instead specifies tolerable data loss measured in time.

  • ✗

    Service Level Agreement (SLA)

    Why it's wrong here

    An SLA is a contractual commitment covering service availability and support response, not a recovery-time metric. It is tempting because SLAs often quote restoration targets, but the BCP's two-hour requirement is a Recovery Time Objective (RTO), which specifies the maximum tolerable downtime for critical systems.

  • ✗

    Recovery Point Objective (RPO)

    Why it's wrong here

    RPO defines the maximum acceptable data loss measured backwards from the disruption, expressed as a time interval, not the restoration deadline. It is tempting because both are BCP recovery metrics, but the two-hour requirement concerns downtime, which is the Recovery Time Objective (RTO).

About these practice questions

One of 989 original CC practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CC practice question is part of Courseiva's free ISC2 certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CC exam.