Courseiva

CRISC Information Technology and Security Practice Question

Which of the following is a key component of an IT risk management programme design?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Risk assessment methodology

A risk assessment methodology defines the process for identifying, analyzing, and evaluating risks, which is a core component of any risk management programme.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Incident response playbooks

    Why it's wrong here

    Incident response playbooks are operational procedures executed after a risk eventuates, not a design component of the risk management programme itself. They belong to incident management, whereas programme design covers risk appetite, governance structures and assessment methodologies.

  • ✓

    Risk assessment methodology

    Why this is correct

    A risk assessment methodology defines how risks are identified, analysed, evaluated and prioritised, forming the foundation on which the entire IT risk management programme operates. Without it, consistent scoring and treatment decisions across the organisation are impossible.

  • ✗

    Vendor security assessment reports

    Why it's wrong here

    Vendor security assessment reports document third-party control posture; they are an input to risk evaluation, not a design component of the programme itself. They are tempting because supplier risk genuinely belongs within risk management, and such reports would be the right artefact when assessing a specific vendor's residual risk during due diligence.

  • ✗

    Network topology diagrams

    Why it's wrong here

    Network topology diagrams are technical architecture artefacts describing infrastructure layout, not a structural element of risk programme design. They support risk assessment as inputs, while the programme itself comprises governance, risk appetite, roles and reporting processes.

About these practice questions

Courseiva writes every CRISC question from scratch — 1,062 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.