Sequence the steps for conducting a business impact analysis (BIA).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Identify critical processes, then determine outage tolerance, then identify dependencies, then estimate impact, then prioritize
BIA involves identifying critical processes, outage tolerance, dependencies, impact estimation, and prioritization.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Identify critical processes, then determine outage tolerance, then identify dependencies, then estimate impact, then prioritize
Why this is correct
This is the correct sequence because BIA starts with identifying critical processes to know what is essential, then determines outage tolerance to set recovery targets, identifies dependencies to understand what supports those processes, estimates impact to quantify losses, and finally prioritizes based on criticality and impact.
- ✗
Identify critical processes, then identify dependencies, then determine outage tolerance, then estimate impact, then prioritize
Why it's wrong here
This sequence is incorrect because outage tolerance should be determined before identifying dependencies; understanding how long a process can be down helps define which dependencies are critical and their required recovery times.
- ✗
Identify critical processes, then estimate impact, then determine outage tolerance, then identify dependencies, then prioritize
Why it's wrong here
This is wrong because impact estimation depends on outage tolerance (e.g., financial loss per hour), so tolerance must be determined before impact. Estimating impact first without tolerance would be speculative.
- ✗
Prioritize, then identify critical processes, then determine outage tolerance, then identify dependencies, then estimate impact
Why it's wrong here
This order is incorrect because prioritization is the final step after all analysis is complete. You cannot prioritize processes before identifying them and assessing their tolerance, dependencies, and impact.
Go deeper
Related to this question
About these practice questions
One of 983 original CRISC practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.