During a risk identification workshop, the team identifies a potential data leakage from a legacy system. What is the FIRST step the risk owner should take?

⚠ Common exam trap

The trap here is that candidates often jump to immediate remediation (like encryption) or escalation, forgetting that formal documentation is the mandatory first step to ensure traceability and compliance with risk management processes.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Document the risk and its source

The first step for the risk owner is to formally document the risk and its source. This ensures that the identified data leakage from the legacy system is captured in the risk register, establishing a baseline for analysis and treatment. Without documentation, subsequent steps like risk scoring, control implementation, or escalation cannot be properly justified or tracked.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Implement encryption immediately

    Why it's wrong here

    Implementing encryption addresses a symptom before the risk is understood; the risk owner must first assess likelihood and impact to determine whether treatment is warranted. Encryption is a control selection activity, appropriate later in risk response, once analysis confirms data leakage exposure exceeds the organisation's defined risk appetite and treatment is prioritised.

  • ✓

    Document the risk and its source

    Why this is correct

    Recording the risk and its source in the risk register creates the documented basis for subsequent analysis, evaluation and treatment. Until captured, the data leakage cannot be assessed or assigned, so documentation is the prerequisite first step before any response.

  • ✗

    Assign a risk score

    Why it's wrong here

    Scoring requires an assessed likelihood and impact, which do not yet exist for an unanalysed risk. It is tempting because scoring prioritises treatment, and would be correct once the risk has been analysed and its likelihood and impact determined.

  • ✗

    Report to senior management

    Why it's wrong here

    Escalation to senior management is a communication step, not risk identification; the risk owner must first analyse the legacy system's exposure and document the scenario before anyone can act on it. Reporting upward is tempting because governance demands oversight, and it would be right once a validated, prioritised risk needs a funding or acceptance decision.

About these practice questions

Courseiva writes every CRISC question from scratch — 1,062 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.