Courseiva
mediumMultiple ChoiceObjective-mapped

CRISC Practice Question: During a risk assessment, a risk practitioner…

During a risk assessment, a risk practitioner identifies that a legacy application uses a deprecated encryption protocol. The application is critical for business operations and cannot be patched. Which of the following is the BEST approach to assess the risk?

⚠ Common exam trap

A common mix-up: candidates confuse risk assessment with risk treatment, mistakenly selecting Option A (replacement) or Option D (escalation) as the 'best approach' when the question specifically asks for the assessment step, not the remediation step.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the threat landscape and existing compensating controls to determine residual risk

The best approach to assess risk for a legacy application using a deprecated encryption protocol (e.g., SSL 3.0 or TLS 1.0) is to analyze the threat landscape and existing compensating controls. This allows the risk practitioner to determine the residual risk by considering factors such as whether the application is only accessible on an isolated network segment, whether network-level encryption (e.g., IPsec or a VPN tunnel) is in place, and whether the protocol is vulnerable to specific attacks like POODLE or BEAST. Simply assigning a high inherent risk score without further analysis (Option C) ignores compensating controls, while immediate escalation (Option D) or replacement (Option A) are risk treatment decisions, not risk assessment activities.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Replace the application with a modern alternative

    Why it's wrong here

    Not part of risk assessment; it's a risk treatment decision after assessment.

  • Analyze the threat landscape and existing compensating controls to determine residual risk

    Why this is correct

    Proper assessment involves analyzing threats and compensating controls to estimate residual risk.

  • Assign a high inherent risk score without further analysis

    Why it's wrong here

    Inherent risk should be assessed based on likelihood and impact, but residual risk requires control evaluation.

  • Immediately escalate to senior management for an exception

    Why it's wrong here

    Escalation should follow documented risk acceptance process after assessment.

Quick reference

VPN Protocol Comparison

ProtocolPortEncryptionAuthenticationUse Case
IKEv2 / IPsecUDP 500 / 4500AES-256Certificates / PSKSite-to-site & remote access
SSL / TLS VPNTCP 443TLS 1.3Certificates / MFAClientless remote access
L2TP / IPsecUDP 1701AES (IPsec)PSK / CertificatesLegacy remote access
WireGuardUDP 51820ChaCha20Public keysModern high-performance VPN
PPTPTCP 1723MPPE (weak)MS-CHAPv2Legacy — avoid in production

PPTP is considered insecure. IKEv2/IPsec and SSL VPN are the current recommended options.

About these practice questions

This CRISC question is part of Courseiva's 983-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.