Courseiva

CRISC Risk Response and Reporting Practice Question

An organization is implementing a new access control system. Which of the following should be included in the control implementation plan?

⚠ Common exam trap

CRISC often tests the distinction between inputs to risk management processes and the components of implementation plans, causing candidates to confuse risk assessment results or KRIs as part of the plan rather than as separate elements.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project milestones, training schedule, and documentation updates

The control implementation plan must be actionable and comprehensive, covering the practical steps needed to deploy the new access control system. Option C includes project milestones (timeline), training schedule (ensuring users and administrators know how to use the system), and documentation updates (keeping policies, procedures, and system documentation current). These elements are essential for a successful implementation and align with CRISC's focus on integrating risk management into business processes. The other options are either too narrow (cost only) or are inputs to the plan rather than components of the plan itself.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Annual cost of the control only

    Why it's wrong here

    Cost alone omits the control's scope, ownership, testing, monitoring and residual risk treatment that an implementation plan must define. Budget figures are tempting because funding approval is a genuine gate, and a cost-benefit analysis belongs in the business case. The plan itself must instead document how the control is deployed, operated and verified.

  • ✗

    Key Risk Indicators (KRIs) for the control

    Why it's wrong here

    KRIs measure whether risk exposure is trending beyond appetite during live operation; they are monitoring instruments, not implementation deliverables. They are tempting because the access control will eventually need ongoing measurement. An implementation plan instead captures design, scope, responsibilities, timelines and the risk assessment results justifying the control.

  • ✓

    Project milestones, training schedule, and documentation updates

    Why this is correct

    Project milestones, training schedule, and documentation updates constitute the implementation plan's core components, ensuring the control is deployed on time, users are trained, and records reflect the change. This satisfies the stem's requirement for what belongs in a control implementation plan, covering delivery, competence, and audit evidence.

  • ✗

    Risk assessment results

    Why it's wrong here

    Risk assessment results identify which risks the access control addresses and justify its selection, but they precede the plan rather than forming part of it. They are tempting because they anchor the control's rationale. The implementation plan itself must specify scope, ownership, deployment steps, testing and monitoring arrangements for the new system.

About these practice questions

Courseiva writes every CRISC question from scratch — 1,062 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official ISACA exam blueprint

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.