Courseiva
IT Risk AssessmenteasyMultiple ChoiceObjective-mapped

CRISC IT Risk Assessment Practice Question

An organization decides to discontinue a high-risk business process that cannot be effectively mitigated. This is an example of which risk treatment option?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk avoidance

Avoidance involves eliminating the activity that creates the risk, thus removing the risk entirely.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk acceptance

    Why it's wrong here

    Acceptance means continuing the activity and accepting the risk.

  • Risk transfer

    Why it's wrong here

    Transfer involves shifting risk to a third party.

  • Risk mitigation

    Why it's wrong here

    Mitigation would involve controls, not discontinuation.

  • Risk avoidance

    Why this is correct

    Correct. Discontinuing the process avoids the risk.

About these practice questions

Courseiva writes every CRISC question from scratch — 983 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.