Courseiva
IT Risk Assessment →hardMultiple Choice

CRISC IT Risk Assessment Practice Question

After implementing controls, the risk remaining is called:

⚠ Common exam trap

CRISC often tests the distinction between residual risk (remaining after controls) and acceptable risk (the threshold the organization tolerates) — candidates pick 'acceptable risk' because it sounds like the endpoint, but the question asks for the remaining risk itself.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Residual risk

Residual risk is the risk that remains after controls have been implemented to mitigate the original (inherent) risk. It represents the exposure the organization still carries and must consciously accept, transfer, or further mitigate. This is a core CRISC definition tested repeatedly.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Control risk

    Why it's wrong here

    Control risk measures the possibility that a control fails to prevent or detect a problem, not the exposure left after controls operate. Residual risk is the remaining exposure once controls are applied. Control risk would be correct when assessing the reliability of an individual control's design or operation.

  • ✗

    Acceptable risk

    Why it's wrong here

    Acceptable risk is a judgement that residual exposure falls within the organisation's tolerance threshold; it is not the term for the exposure itself. Residual risk is what remains after controls are implemented. Acceptable risk would be correct when documenting that the remaining exposure has been formally tolerated.

  • ✓

    Residual risk

    Why this is correct

    Residual risk is the exposure that remains after controls have been implemented and inherent risk has been mitigated. It represents the gap between total risk and the effect of existing controls, which is precisely what the question describes following control implementation.

  • ✗

    Inherent risk

    Why it's wrong here

    Inherent risk is the exposure before any controls are applied, so it describes the starting position, not what remains afterwards. Residual risk is the exposure left once controls are operating. Inherent risk would be the correct term when assessing risk at the initial identification stage, prior to mitigation.

About these practice questions

This CRISC question is part of Courseiva's 1,062-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official ISACA exam blueprint

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.