Courseiva
IT Risk AssessmentmediumMultiple ChoiceObjective-mapped

CRISC IT Risk Assessment Practice Question

After implementing a set of controls, the risk owner calculates the residual risk. Which of the following is true about residual risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

It is the risk that remains after controls are applied

Residual risk is the risk remaining after controls are applied, and it should be within the risk appetite.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • It is the risk that remains after controls are applied

    Why this is correct

    Residual risk = inherent risk adjusted for control effectiveness.

  • It is not considered in risk treatment decisions

    Why it's wrong here

    Residual risk is key for deciding if additional treatment is needed.

  • It is always higher than inherent risk

    Why it's wrong here

    Controls reduce risk, so residual risk is lower than inherent.

  • It is the risk before any controls are implemented

    Why it's wrong here

    That describes inherent risk.

About these practice questions

One of 983 original CRISC practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.