CRISC IT Risk Identification Practice Question
A risk register is being created for a new ERP implementation project. Which TWO of the following risks should be included in the project's risk register? (Choose two.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk of project delays due to resource shortages
Project risks include delays, budget overruns, and scope changes. Data breach and regulatory non-compliance are operational/compliance risks that may apply post-implementation but are not specific to the project's execution.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk of data breach due to misconfigured cloud storage
Why it's wrong here
This is an operational risk, not specifically a project risk.
- ✗
Risk of regulatory non-compliance with new data protection laws
Why it's wrong here
This is a compliance risk, may be relevant after go-live.
- ✓
Risk of project delays due to resource shortages
Why this is correct
Correct. Resource shortage is a common project risk.
- ✓
Risk of budget overrun due to scope creep
Why this is correct
Correct. Scope creep is a typical project risk.
- ✗
Risk of hardware failure in the data center
Why it's wrong here
This is an operational risk, not project-specific.
Go deeper
Related to this question
About these practice questions
This CRISC question is part of Courseiva's 983-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.