Courseiva

CISM Information Security Risk Management Practice Question

After implementing controls, an organization reassesses a risk and finds that the residual risk level exceeds the established risk tolerance. What is the most appropriate next step?

⚠ Common exam trap

The CISM exam often tests the misconception that risk assessment methodology changes can resolve residual risk issues, but the trap here is that candidates may choose Option A, thinking a different methodology will yield a more favorable result, when in fact the correct action is to treat the risk through additional controls or formal acceptance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Seek management approval for acceptance or implement additional controls

When residual risk exceeds the established risk tolerance, the organization must either implement additional controls to reduce the risk further or formally accept the residual risk through management approval. This aligns with the risk treatment decision-making process in ISO 31000 and the CISM framework, where risk acceptance is a management responsibility. Option C correctly identifies these two valid paths.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Re-assess the risk using a different methodology

    Why it's wrong here

    Swapping methodology does not alter the residual risk level or bring it within tolerance; it merely re-labels the same exposure. It tempts because reassessment feels rigorous, and methodology changes are legitimate when the existing approach is demonstrably flawed, not when results are unwelcome.

  • ✗

    Lower the risk tolerance to match the residual risk

    Why it's wrong here

    Lowering tolerance to match the residual risk inverts the framework: tolerance is set by management appetite and drives treatment, not the reverse. It tempts because it appears to close the gap cheaply, and tolerance revision is valid when business strategy genuinely changes.

  • ✓

    Seek management approval for acceptance or implement additional controls

    Why this is correct

    Residual risk above tolerance cannot simply be left; the risk owner must decide. Either obtain formal management approval to accept the elevated exposure or apply further controls to bring it within tolerance, preserving accountability and documented risk ownership.

  • ✗

    Ignore the residual risk since controls are already in place

    Why it's wrong here

    Ignoring residual risk above tolerance leaves the organisation knowingly exposed and breaches governance obligations to treat unacceptable risk. It tempts because implemented controls create a false sense of completion, and acceptance is valid only when residual risk already sits within tolerance.

About these practice questions

This CISM question is part of Courseiva's 924-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISM practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISM exam.