Question 221 of 509

Quick Answer

The answer is the updated project schedule with actual completion dates for milestones. This provides the best evidence of project schedule progress because it directly compares the baseline plan against real-world performance, showing exact completion dates and variance analysis, which allows an IS auditor to objectively assess whether the system development project is on schedule. On the CISA exam, this question tests your understanding of project management controls and the distinction between subjective status reports and objective, verifiable artifacts—a common trap is choosing a status meeting or a Gantt chart without actual dates, which only shows intent, not evidence. Remember the memory tip: “Actual dates beat stated fates”—only documented completion dates prove true progress against the planned timeline.

CISA Practice Question: Information Systems Acquisition, Development and Implementation

This CISA practice question tests your understanding of information systems acquisition, development and implementation. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

An IS auditor is reviewing a system development project to assess whether it is on schedule. Which of the following would provide the BEST evidence of project progress against the planned timeline?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "best"

    Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Updated project schedule with actual completion dates for milestones

The updated project schedule with actual completion dates for milestones (Option D) provides direct, objective evidence of progress against the planned timeline. It shows the baseline plan, the actual dates work was completed, and the variance, allowing the IS auditor to quantitatively assess schedule adherence. This is the primary artifact for schedule tracking in system development projects.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Minutes from status review meetings

    Why it's wrong here

    Minutes are subjective and may not reflect actual timeline performance.

  • Approved requirements document

    Why it's wrong here

    Approved requirements are a baseline, not progress.

  • Successful unit test results

    Why it's wrong here

    Unit tests show technical completion, not schedule adherence.

  • Updated project schedule with actual completion dates for milestones

    Why this is correct

    The project schedule directly compares planned vs actual milestones.

    Clue confirmation

    The clue word "best" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse evidence of technical progress (like passing unit tests) with evidence of schedule progress, failing to recognize that technical success does not equate to on-time delivery.

Trap categories for this question

  • Command / output trap

    Unit tests show technical completion, not schedule adherence.

Detailed technical explanation

How to think about this question

In project management, the project schedule is a dynamic artifact that is baselined at the start and then updated with actual start/finish dates and remaining durations. The IS auditor compares the baseline against the actuals to compute schedule variance (SV) using earned value management (EVM) metrics like SPI = EV/PV. A schedule with actual dates enables the auditor to identify critical path delays, float consumption, and trend analysis, which are essential for assessing the true health of the project timeline.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CISA exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CISA practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CISA practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CISA question test?

Information Systems Acquisition, Development and Implementation — This question tests Information Systems Acquisition, Development and Implementation — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Updated project schedule with actual completion dates for milestones — The updated project schedule with actual completion dates for milestones (Option D) provides direct, objective evidence of progress against the planned timeline. It shows the baseline plan, the actual dates work was completed, and the variance, allowing the IS auditor to quantitatively assess schedule adherence. This is the primary artifact for schedule tracking in system development projects.

What should I do if I get this CISA question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 25, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.