Courseiva
mediumMultiple Choice

CISA Practice Question: During system development, the project team…

During system development, the project team discovers that the original requirements are incomplete. What is the BEST course of action?

⚠ Common exam trap

Test-takers frequently choose Option D (halting the project) because they assume all requirements must be fully finalized before development, but the CISA exam emphasizes that change management is the appropriate mechanism to handle evolving requirements without stopping the project entirely.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Formally document the new requirements and follow the change management process

Formally documenting new requirements and following the change management process ensures that all changes are controlled, assessed for impact on scope, budget, and schedule, and approved by stakeholders. This aligns with the systems development lifecycle (SDLC) best practices and the ISACA standard for managing requirements changes, preventing scope creep and maintaining project integrity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Formally document the new requirements and follow the change management process

    Why this is correct

    Undocumented scope changes undermine traceability and testing. Formally recording the new requirements and routing them through change management ensures impact assessment, approval and updated baselines, keeping the system aligned with business needs and audit expectations.

  • ✗

    Inform the steering committee and continue as planned

    Why it's wrong here

    Continuing as planned without resolving the gaps leaves the steering committee approving a baseline that cannot deliver the intended system, so scope decisions lack governance input. It is tempting to keep sponsors informed, but escalation must accompany a revised requirements baseline, not unchanged execution.

  • ✗

    Proceed with development and address changes during maintenance

    Why it's wrong here

    Deferring incomplete requirements to maintenance lets defects and rework compound through design, build and testing, since maintenance cannot retroactively correct a flawed baseline. It is tempting when schedule pressure dominates, but maintenance is for post-implementation fixes, not unresolved scope.

  • ✗

    Halt the project until all requirements are finalized

    Why it's wrong here

    Halting the entire project over incomplete requirements stalls unrelated workstreams and delays delivery without first assessing which gaps are material. It is tempting as a cautious response, but the correct action is to analyse and close the requirement gaps through change control, not freeze all activity.

About these practice questions

Courseiva writes every CISA question from scratch — 934 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.