Courseiva

CISA Practice Question: Information Systems Acquisition, Development, and Implementation

During an agile software development project, which of the following events provides the best opportunity for the IS auditor to assess the effectiveness of controls implemented in the current sprint?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Sprint review

The sprint review is a demonstration of working software where controls can be observed. The retrospective is about process improvement, not control assessment.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Sprint planning meeting

    Why it's wrong here

    Sprint planning defines the backlog, but does not demonstrate controls.

  • Sprint review

    Why this is correct

    The sprint review allows the auditor to see working functionality and verify controls.

  • Daily standup meeting

    Why it's wrong here

    Daily standups are for coordination, not control assessment.

  • Sprint retrospective

    Why it's wrong here

    The retrospective focuses on process improvement, not control verification.

About these practice questions

Courseiva writes every CISA question from scratch — 995 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.