Question 443 of 509

Quick Answer

The answer is to conduct a root cause analysis to identify the reasons for the cost overrun. This is correct because the earned value management cost variance root cause analysis reveals that the project is both over budget, with an EV of $500,000 against an AC of $600,000, and behind schedule, as the EV is less than the PV of $550,000. Before any corrective action can be taken, the project manager must first understand why the cost variance occurred, ensuring that the fix addresses the underlying issue rather than just the symptom. On the Certified Information Systems Auditor CISA exam, this scenario tests your understanding of the control process: you must diagnose before you treat. A common trap is jumping straight to budget reallocation or scope changes, but the CISA framework prioritizes investigation over action. Remember the mnemonic “D-I-A” for variances: Diagnose (root cause), Investigate (data), then Act (corrective measures).

CISA Practice Question: Information Systems Acquisition, Development and Implementation

This CISA practice question tests your understanding of information systems acquisition, development and implementation. Compare every option against the stated constraints before choosing — the best answer satisfies all requirements, not just the most obvious one. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a system development project, the project manager notices that the actual cost is significantly higher than the planned cost at the 50% completion point. The earned value (EV) is $500,000, the actual cost (AC) is $600,000, and the planned value (PV) is $550,000. Which of the following is the MOST appropriate action?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Conduct a root cause analysis to identify the reasons for cost overrun

Option C is correct because the project is over budget (EV $500K vs AC $600K) and behind schedule (EV $500K vs PV $550K). Before taking corrective action, the project manager must first perform a root cause analysis to understand why costs are exceeding planned values. This aligns with the CISA’s emphasis on identifying the underlying cause of variances before implementing changes to scope, budget, or schedule.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Request additional budget from senior management

    Why it's wrong here

    This does not address the root cause of cost overrun.

  • Reduce the project scope to align with the budget

    Why it's wrong here

    Scope reduction is a last resort; first understand why costs are high.

  • Conduct a root cause analysis to identify the reasons for cost overrun

    Why this is correct

    Understanding the cause is the first step before taking corrective action.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Crash the project schedule to make up for lost time

    Why it's wrong here

    The project is behind schedule, but crashing would increase costs further.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often jump to a corrective action (like crashing or requesting more budget) without first diagnosing the root cause, but the CISA exam emphasizes that analysis must precede action in project management.

Detailed technical explanation

How to think about this question

Earned Value Management (EVM) uses three key metrics: Planned Value (PV), Earned Value (EV), and Actual Cost (AC). At 50% completion, the Cost Performance Index (CPI = EV/AC) is 0.833, indicating that for every dollar spent, only $0.83 of work is earned. The Schedule Performance Index (SPI = EV/PV) is 0.909, showing the project is behind schedule. Root cause analysis (e.g., using a fishbone diagram or 5 Whys) is the first step in the Plan-Do-Check-Act cycle to identify whether the variance stems from inaccurate estimates, resource inefficiency, or external dependencies before any corrective action is taken.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CISA exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CISA practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CISA practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CISA question test?

Information Systems Acquisition, Development and Implementation — This question tests Information Systems Acquisition, Development and Implementation — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Conduct a root cause analysis to identify the reasons for cost overrun — Option C is correct because the project is over budget (EV $500K vs AC $600K) and behind schedule (EV $500K vs PV $550K). Before taking corrective action, the project manager must first perform a root cause analysis to understand why costs are exceeding planned values. This aligns with the CISA’s emphasis on identifying the underlying cause of variances before implementing changes to scope, budget, or schedule.

What should I do if I get this CISA question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.