- A
Regular status meetings
Why wrong: Meetings help communication but do not ensure timeliness.
- B
A realistic project schedule with milestones
A realistic schedule with milestones provides a clear plan and tracking.
- C
Frequent scope changes
Why wrong: Scope changes typically cause delays.
- D
Use of a project management software
Why wrong: Software is a tool, not a method to ensure timeliness.
Quick Answer
The answer is a realistic project schedule with milestones. This is the best method to ensure project completion on time because it establishes a time-phased baseline with measurable checkpoints, allowing project managers to detect delays early and take corrective action before the schedule slips irreparably. Without a realistic schedule, even the most rigorous tracking tools or status meetings cannot prevent overruns, as the schedule itself is the foundation for monitoring and controlling progress. On the CISA exam, this concept tests your understanding of project management controls within the Systems Development Life Cycle (SDLC); a common trap is choosing “frequent status meetings” or “earned value management” as the best method, but these are only effective if anchored to a realistic baseline. Remember the memory tip: “No baseline, no control—milestones make delays visible.”
CISA Practice Question: Information Systems Acquisition, Development and Implementation
This CISA practice question tests your understanding of information systems acquisition, development and implementation. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which of the following is the BEST method to ensure that a system development project is completed on time?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"best"Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
A realistic project schedule with milestones
A realistic project schedule with milestones (Option B) is the best method because it establishes a time-phased plan with measurable checkpoints, enabling early detection of delays and facilitating proactive corrective actions. Without a realistic baseline, even the best tracking tools or meetings cannot prevent schedule overruns, as the schedule itself is the foundation for monitoring and controlling project progress.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Regular status meetings
Why it's wrong here
Meetings help communication but do not ensure timeliness.
- ✓
A realistic project schedule with milestones
Why this is correct
A realistic schedule with milestones provides a clear plan and tracking.
Clue confirmation
The clue word "best" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Frequent scope changes
Why it's wrong here
Scope changes typically cause delays.
- ✗
Use of a project management software
Why it's wrong here
Software is a tool, not a method to ensure timeliness.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse project management tools or meetings with the fundamental planning artifact (the schedule) that actually drives on-time delivery, leading them to select a supporting activity (like status meetings or software) instead of the core control mechanism.
Detailed technical explanation
How to think about this question
A realistic project schedule is built using techniques like Work Breakdown Structure (WBS) decomposition, critical path method (CPM) analysis, and three-point estimation (PERT) to account for task dependencies and uncertainty. Milestones serve as control gates where deliverables are formally reviewed, allowing the project manager to apply earned value management (EVM) metrics (e.g., SPI, CPI) to objectively measure schedule performance and forecast completion dates. In practice, a schedule that ignores resource leveling or fails to incorporate buffer time for high-risk tasks will inevitably slip, regardless of how many meetings or tools are used.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the CISA exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Information Systems Acquisition, Development and Implementation — study guide chapter
Learn the concepts, then practise the questions
- →
Information Systems Acquisition, Development and Implementation practice questions
Targeted practice on this topic area only
- →
All CISA questions
509 questions across all exam domains
- →
Certified Information Systems Auditor CISA study guide
Full concept coverage aligned to exam objectives
- →
CISA practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related CISA practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Governance and Management of IT practice questions
Practise CISA questions linked to Governance and Management of IT.
Information Systems Acquisition, Development and Implementation practice questions
Practise CISA questions linked to Information Systems Acquisition, Development and Implementation.
Information Systems Operations and Business Resilience practice questions
Practise CISA questions linked to Information Systems Operations and Business Resilience.
Protection of Information Assets practice questions
Practise CISA questions linked to Protection of Information Assets.
Information System Auditing Process practice questions
Practise CISA questions linked to Information System Auditing Process.
CISA fundamentals practice questions
Practise CISA questions linked to CISA fundamentals.
CISA scenario practice questions
Practise CISA questions linked to CISA scenario.
CISA troubleshooting practice questions
Practise CISA questions linked to CISA troubleshooting.
Practice this exam
Start a free CISA practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this CISA question test?
Information Systems Acquisition, Development and Implementation — This question tests Information Systems Acquisition, Development and Implementation — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: A realistic project schedule with milestones — A realistic project schedule with milestones (Option B) is the best method because it establishes a time-phased plan with measurable checkpoints, enabling early detection of delays and facilitating proactive corrective actions. Without a realistic baseline, even the best tracking tools or meetings cannot prevent schedule overruns, as the schedule itself is the foundation for monitoring and controlling project progress.
What should I do if I get this CISA question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More CISA practice questions
- An organization is implementing a new financial system and has completed user acceptance testing (UAT). The project mana…
- An organization is implementing a data loss prevention (DLP) solution. Which TWO of the following are key considerations…
- Based on the exhibit, which control is most likely missing to prevent this type of event?
- Arrange the steps to perform a risk assessment in the correct order.
- Order the steps for conducting an audit engagement from start to finish.
- Order the steps for responding to a security incident in the correct sequence.
Last reviewed: Jun 25, 2026
This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.