An IS auditor is evaluating the change management process. Which of the following is the BEST indicator that emergency changes are being properly controlled?

⚠ Common exam trap

CISA often tests the misconception that emergency changes should still go through full pre-approval or testing — the correct control is post-implementation review and documentation, not pre-approval.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Emergency changes are documented with a justification and promptly reviewed after implementation

The best indicator that emergency changes are properly controlled is that they are documented with a justification and promptly reviewed after implementation. Emergency changes, by definition, bypass the normal pre-approval and testing cycle, so the compensating control is retrospective review and documentation to ensure accountability and to catch any issues. This aligns with ITIL and COBIT guidance that emergency changes must be logged, justified, and reviewed post-implementation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Emergency changes are documented with a justification and promptly reviewed after implementation

    Why this is correct

    Documenting each emergency change with justification and reviewing it promptly afterwards confirms the control operated: the change was authorised retrospectively and assessed, rather than bypassing governance entirely, which is the strongest evidence of proper control.

  • ✗

    Emergency changes are approved by the change manager within 24 hours

    Why it's wrong here

    A 24-hour approval window permits the change to be implemented before any authorisation exists, leaving the emergency change uncontrolled during execution. Change manager approval is appropriate for standard changes, where the approval occurs before, not after, implementation begins.

  • ✗

    Emergency changes are tested in a production-like environment before implementation

    Why it's wrong here

    Emergency changes typically bypass pre-implementation testing because the fix is urgent; requiring production-like testing contradicts the emergency definition and delays restoration. Testing before release is the correct control for normal, planned changes, where scheduled windows allow validation without extending outage time.

  • ✗

    Emergency changes require approval from the CAB before implementation

    Why it's wrong here

    Requiring full CAB approval before implementation defeats the purpose of an emergency change, which exists to restore service outside the normal CAB cycle. Pre-approval by the CAB is the correct control for routine changes, where scheduled review does not delay urgent remediation.

About these practice questions

One of 934 original CISA practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva