AAIR AI Lifecycle Risk Management Practice Question
A practitioner is managing AI risk in a CI/CD pipeline. What should be the final gate before model promotion to production?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Automated performance validation against a hold-out test set with defined threshold gates.
Automated validation of performance metrics against a 'golden dataset' ensures the model meets the required threshold.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Increasing the memory of the production server.
Why it's wrong here
Resource allocation is a deployment step, not a promotion gate.
- ✗
Updating the project's documentation.
Why it's wrong here
Documentation can be updated independently of the deployment.
- ✓
Automated performance validation against a hold-out test set with defined threshold gates.
Why this is correct
This ensures the model satisfies quantitative quality criteria before reaching production.
- ✗
A peer review of the training code.
Why it's wrong here
Peer review is important, but not sufficient as a final gate.
About these practice questions
This AAIR question is part of Courseiva's 199-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official ISACA exam blueprint