1
Project Management Concepts
hard
A project manager is preparing the resource management plan for a project that requires a scarce cybersecurity specialist for only three weeks of a nine-month schedule. The functional manager has warned that the specialist may be pulled onto a higher-priority incident at any time. Which action should the PM take to protect the schedule?