Question 87 of 503
Vulnerability ManagementmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is to update the risk register with the owner, justification, expiry date, and compensating controls. This is correct because formal risk acceptance requires documented evidence that the decision was deliberate, time-bound, and mitigated by alternative safeguards, ensuring the risk does not become a permanent vulnerability. On the CompTIA CySA+ CS0-003 exam, this tests your understanding of vulnerability management governance and the risk register update for patch delay acceptance as a formal process, not just a note. A common trap is to think the scanner configuration or pipeline should be changed to force the patch, but the business unit has already accepted the risk, so the register is the authoritative record. Memory tip: think "OJEC" — Owner, Justification, Expiry, Compensating controls — to remember the four required fields for any accepted risk entry.

CS0-003 Vulnerability Management Practice Question

This CS0-003 practice question tests your understanding of vulnerability management. This is a configuration task: choose the command set that satisfies every stated requirement. Small differences — like 'secret' vs 'password' or 'transport input ssh' vs 'all' — change whether the answer is correct. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A business unit accepts the risk of delaying a patch because downtime would breach a contractual deadline. What should be updated? For tool configuration, Which scanner or pipeline change most directly improves result quality?

Question 1mediummultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The risk register with owner, justification, expiry date, and compensating controls

When a business unit formally accepts the risk of delaying a patch, the risk must be documented in the risk register with an owner, justification, an expiry date, and compensating controls. This ensures the risk is tracked, reviewed, and mitigated within an acceptable timeframe, which is a core requirement of vulnerability management governance.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The firewall vendor invoice

    Why it's wrong here

    Invoices do not record risk decisions.

  • The risk register with owner, justification, expiry date, and compensating controls

    Why this is correct

    Risk acceptance must be explicit, time-bound, owned, and controlled.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The incident containment playbook only

    Why it's wrong here

    This is a vulnerability-risk decision, not necessarily an incident.

  • The phishing training completion list

    Why it's wrong here

    Training data does not document accepted patch risk.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Cisco often tests the distinction between operational documentation (risk register) and reactive documentation (incident playbook), tricking candidates into choosing the incident playbook because they confuse risk acceptance with incident response.

Detailed technical explanation

How to think about this question

A risk register typically includes fields such as risk ID, asset affected, vulnerability CVE, likelihood, impact, risk score, owner, justification, expiry date, and compensating controls. Compensating controls might include network segmentation, intrusion detection rules, or manual monitoring to reduce the risk until the patch is applied. The expiry date ensures the risk is re-evaluated and the patch is applied before the deadline passes.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

An employee at a financial services firm receives an email that appears to come from the IT helpdesk, asking them to reset their password via a link. The link leads to a convincing fake portal that harvests credentials. Security teams use phishing simulations and security-awareness training to reduce this attack vector. Questions like this test whether you can identify social engineering techniques and appropriate controls.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CS0-003 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CS0-003 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CS0-003 question test?

Vulnerability Management — This question tests Vulnerability Management — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The risk register with owner, justification, expiry date, and compensating controls — When a business unit formally accepts the risk of delaying a patch, the risk must be documented in the risk register with an owner, justification, an expiry date, and compensating controls. This ensures the risk is tracked, reviewed, and mitigated within an acceptable timeframe, which is a core requirement of vulnerability management governance.

What should I do if I get this CS0-003 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

4 more ways this is tested on CS0-003

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A business unit accepts the risk of delaying a patch because downtime would breach a contractual deadline. What should be updated? For validation, Which action should be taken before closing or downgrading the finding?

medium
  • A.The risk register with owner, justification, expiry date, and compensating controls
  • B.The firewall vendor invoice
  • C.The incident containment playbook only
  • D.The phishing training completion list

Why A: When a business unit formally accepts the risk of delaying a patch due to contractual constraints, the risk must be documented in the risk register. This entry should include the owner, justification, expiry date, and compensating controls to ensure the risk is tracked, reviewed, and eventually remediated. This aligns with the vulnerability management lifecycle, where accepted risks require formal documentation and periodic reassessment.

Variation 2. A business unit accepts the risk of delaying a patch because downtime would breach a contractual deadline. What should be updated? For stakeholder management, Which documentation or approval is required to keep the programme defensible?

medium
  • A.The risk register with owner, justification, expiry date, and compensating controls
  • B.The firewall vendor invoice
  • C.The incident containment playbook only
  • D.The phishing training completion list

Why A: When a business unit formally accepts the risk of delaying a patch, the risk register must be updated with the owner, justification, expiry date, and compensating controls. This documentation ensures the decision is defensible during audits or incidents, as it captures the explicit risk acceptance and the temporary controls in place until the patch is applied.

Variation 3. A business unit accepts the risk of delaying a patch because downtime would breach a contractual deadline. What should be updated? For control selection, Which control best addresses the stated weakness without hiding risk?

medium
  • A.The phishing training completion list
  • B.The risk register with owner, justification, expiry date, and compensating controls
  • C.The firewall vendor invoice
  • D.The incident containment playbook only

Why B: Option B is correct because when a business unit accepts the risk of delaying a patch, the risk register must be updated to formally document the risk acceptance. This update should include the risk owner, the business justification for the delay, an expiry date for the exception, and any compensating controls (e.g., network segmentation, enhanced monitoring) that reduce the risk during the gap. This ensures the risk is tracked, reviewed, and eventually remediated, aligning with vulnerability management best practices.

Variation 4. A business unit accepts the risk of delaying a patch because downtime would breach a contractual deadline. What should be updated? For business prioritization, Which recommendation gives the best risk-based order of work?

medium
  • A.The incident containment playbook only
  • B.The firewall vendor invoice
  • C.The risk register with owner, justification, expiry date, and compensating controls
  • D.The phishing training completion list

Why C: When a business unit formally accepts the risk of delaying a patch due to contractual constraints, the risk register must be updated to document the risk owner, justification, expiry date, and compensating controls. This ensures the risk is tracked, reviewed, and mitigated within an acceptable timeframe, aligning with vulnerability management and risk acceptance processes.

Keep practising

More CS0-003 practice questions

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CS0-003 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CS0-003 exam.