200-201 Security Policies and Procedures Practice Question

Which TWO are examples of risk treatment options? (Select two.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Mitigate

Mitigate (B) is a recognized risk treatment option because it involves applying controls or countermeasures to reduce the likelihood and/or impact of a risk to an acceptable level. Accept (D) is also a recognized risk treatment option, meaning the organization acknowledges the risk and decides to retain it without additional controls, typically when the cost of treatment outweighs the benefit or the risk is within tolerance. The other options are not standard risk treatment categories: Neglect (A) and Ignore (C) imply simply disregarding a risk without a formal, documented decision, which is not a valid treatment strategy, and Amplify (E) is not a recognized risk treatment option since treatment aims to reduce or transfer risk, not increase exposure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Neglect

    Why it's wrong here

    Neglect is not a defined risk treatment option; recognised treatments are mitigate, transfer, avoid and accept. It is tempting because ignoring a low-impact risk informally resembles acceptance, but acceptance is a documented, authorised decision, whereas neglect implies no deliberate management.

  • ✓

    Mitigate

    Why this is correct

    Implementing controls to reduce risk.

  • ✗

    Ignore

    Why it's wrong here

    Ignore is not a formal risk treatment option; the recognised treatments are mitigate, transfer, avoid and accept. It is tempting because deliberately disregarding a trivial risk feels like acceptance, but acceptance is an explicit, documented decision, while ignoring implies the risk was never properly assessed.

  • ✓

    Accept

    Why this is correct

    Acceptance is a valid risk treatment where an organisation acknowledges a risk and retains it without additional controls, typically when cost outweighs benefit. It is one of the four recognised treatment options, satisfying the stem's request.

  • ✗

    Amplify

    Why it's wrong here

    Amplify is not a recognised risk treatment option; the standard set is mitigate, transfer, avoid and accept. It is tempting because it sounds like intensifying controls, but no framework defines it as a treatment, so it cannot satisfy the question's requirement for two valid treatments.

About these practice questions

One of 968 original 200-201 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This 200-201 practice question is part of Courseiva's free Cisco certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the 200-201 exam.