Courseiva

200-201 Security Policies and Procedures Practice Question

An organization is reviewing its risk management process and identifies a risk with a high probability and high impact. Management decides to stop the activity causing the risk. Which risk treatment option is being applied?

⚠ Common exam trap

200-201 often tests the distinction between avoidance and mitigation — candidates pick mitigation because 'stopping the activity' sounds like a control, but avoidance specifically means eliminating the activity, not reducing its risk.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Risk avoidance

Risk avoidance is the treatment option where the organization eliminates the risk entirely by discontinuing the activity that creates it. Since management decided to stop the activity causing the high-probability, high-impact risk, this is avoidance. It is the only option that removes the risk rather than reducing, accepting, or transferring it.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Risk mitigation

    Why it's wrong here

    Mitigation reduces the likelihood or impact of a risk while continuing the activity, whereas terminating the activity entirely is risk avoidance. It is tempting because mitigation is the most common treatment, and it would be correct if controls were added rather than the activity stopped.

  • ✗

    Risk acceptance

    Why it's wrong here

    Acceptance means acknowledging the risk and proceeding without action, which contradicts stopping the activity. It is tempting because acceptance is valid for low-probability or low-impact risks, but a high-probability, high-impact risk being eliminated is avoidance, not acceptance.

  • ✓

    Risk avoidance

    Why this is correct

    Risk avoidance eliminates the risk by discontinuing the activity entirely, which matches management stopping the process outright. Unlike mitigation, which reduces likelihood or impact, or transfer, which shifts financial consequence, avoidance removes the exposure at source.

  • ✗

    Risk transfer

    Why it's wrong here

    Stopping the activity is risk avoidance, not transfer, which shifts financial impact to a third party such as an insurer or outsourcer while the activity continues. Transfer is tempting because it is a recognised treatment for high-probability, high-impact risks, but it does not eliminate the underlying activity.

About these practice questions

This 200-201 question is part of Courseiva's 968-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Cisco exam blueprint

This 200-201 practice question is part of Courseiva's free Cisco certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the 200-201 exam.