Courseiva
Security Policies and ProceduresmediumMultiple ChoiceObjective-mapped

200-201 Security Policies and Procedures Practice Question

An organization is reviewing its risk management process and identifies a risk with a high probability and high impact. Management decides to stop the activity causing the risk. Which risk treatment option is being applied?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk avoidance

Avoidance means eliminating the risk by discontinuing the activity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk mitigation

    Why it's wrong here

    Mitigation would reduce, not eliminate, the risk.

  • Risk acceptance

    Why it's wrong here

    Acceptance means acknowledging the risk without action.

  • Risk avoidance

    Why this is correct

    Stopping the activity avoids the risk entirely.

  • Risk transfer

    Why it's wrong here

    Transfer involves shifting risk to another party.

About these practice questions

This 200-201 question is part of Courseiva's 979-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This 200-201 practice question is part of Courseiva's free Cisco certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the 200-201 exam.