Correct answer & explanation
✓
Perform a full system backup using DRS.
DRS (Disaster Recovery System) requires a backup, a clean install of the same version, and a restore operation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Delete the existing TFTP files.
Why it's wrong here
This is not a standard recovery step.
- ✓
Perform a full system backup using DRS.
Why this is correct
The backup is the foundation of the restore.
- ✗
Run the 'utils dbreplication reset' command.
Why it's wrong here
This is for troubleshooting, not recovery.
- ✓
Restore the data using the DRS Restore tool.
Why this is correct
The restore process brings back the configuration.
- ✓
Install a fresh CUCM instance on the new hardware.
Why this is correct
The OS must be at the same version as the backup.
About these practice questions
This CLCOR question is part of Courseiva's 263-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official Cisco exam blueprint
This CLCOR practice question is part of Courseiva's free Cisco certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CLCOR exam.