Drag and drop the steps to migrate an on-premises SAP system to AWS using AWS Application Migration Service (MGN) into the correct order.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Install AWS Replication Agent, then Configure replication settings, then Launch test instances and validate, then Perform cutover, then Perform post-migration steps.
MGN migration involves installing agent, configuring replication, testing, cutover, and post-migration steps.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Install AWS Replication Agent, then Configure replication settings, then Launch test instances and validate, then Perform cutover, then Perform post-migration steps.
Why this is correct
This is the correct order because you must first install the agent to enable replication, then configure replication settings, test the migration with a test instance, perform the final cutover, and finally handle post-migration tasks.
- ✗
Install AWS Replication Agent, then Launch test instances and validate, then Configure replication settings, then Perform cutover, then Perform post-migration steps.
Why it's wrong here
This is incorrect because you cannot launch test instances before configuring replication settings; replication must be configured first to define target details.
- ✗
Configure replication settings, then Install AWS Replication Agent, then Launch test instances and validate, then Perform cutover, then Perform post-migration steps.
Why it's wrong here
This is incorrect because the AWS Replication Agent must be installed on the source server before configuring replication settings; the agent is required to start the replication process.
- ✗
Install AWS Replication Agent, then Configure replication settings, then Perform cutover, then Launch test instances and validate, then Perform post-migration steps.
Why it's wrong here
This is incorrect because performing cutover before testing means you skip validation of the replication and application behavior, which can lead to failures in production.
Go deeper
Related to this question
About these practice questions
One of 1,616 original PAS-C01 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PAS-C01 practice question is part of Courseiva's free Amazon Web Services certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PAS-C01 exam.