You are leading risk management for a global ERP rollout. The program management office has issued a directive that all projects must use a single enterprise risk register with a fixed scoring scale of 1-5 for probability and impact. During a risk workshop, a regional project manager argues that the fixed scale does not reflect the severe regulatory penalties unique to their region. What is the most appropriate action for you as the risk manager?