A company runs its SAP ERP system on AWS. The SAP application servers are in an Auto Scaling group across two Availability Zones. The SAP HANA database runs on a single EC2 instance in us-east-1a. The database instance has an Elastic IP and uses EBS io1 volumes with 5000 provisioned IOPS. During a recent deployment, the company experienced a complete outage when the Availability Zone us-east-1a became unavailable due to a power failure. The database was unavailable for 6 hours until the zone recovered. The company wants to implement a highly available architecture that can automatically recover from an AZ failure with minimal data loss. The Recovery Point Objective (RPO) is 15 minutes and Recovery Time Objective (RTO) is 30 minutes. What should the company do?