A company is designing a disaster recovery solution for a critical application that runs on Amazon EC2 instances in a single AWS Region. The application uses an Amazon RDS for MySQL database. The recovery time objective (RTO) is 1 hour and the recovery point objective (RPO) is 15 minutes. Which combination of steps should the company take to meet these requirements? (Choose THREE.)