1
Process — Managing Technical Aspects
hard
You are managing a construction project. During a quality audit, you find that the concrete used in the foundation does not meet the specified strength requirements. The team has already poured the concrete. The project is on a tight schedule, and rework will delay the project by three weeks. What should you do NEXT?