A project manager is reviewing the project charter and notices that the business case includes a cost-benefit analysis with a Net Present Value (NPV) of $50,000 and an Internal Rate of Return (IRR) of 12%. The company's required rate of return is 10%. What should the project manager conclude about this project?
Select one:
PMI often tests the misconception that a positive NPV alone is sufficient without considering the IR...