Refer to the exhibit. Based on the project status report, what is the cost variance (CV) and what does it indicate?

Exhibit

Project Status Report - Monthly
Budget:
Planned Value (PV): $120,000
Actual Cost (AC): $130,000
Earned Value (EV): $115,000