Which of the following scenarios best demonstrates a 'pull' system in a SAFe ART?
A pull system is characterized by teams taking on new work only when they have available capacity. This prevents the accumulation of work-in-progress, keeps queues short, and ensures that work items move through the system steadily. It is the core mechanism for maintaining flow in a Kanban-based delivery model.
Why this answer
A pull system ensures that work is started only when there is capacity available to process it, preventing the creation of excess inventory or hidden queues. By using signals such as empty slots on a Kanban board, the downstream team informs the upstream team they are ready. This methodology is critical for maintaining a stable, predictable flow throughout the value stream.
Exam trap
Candidates often confuse a pull system with traditional push planning, selecting options where work is assigned by management rather than taken by teams based on available capacity.