Your project sponsor asks you to skip the testing phase of a software release to meet a tight deadline. What is the best response?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Explain the risks of skipping testing, including potential defects and rework, and propose alternatives such as reducing test scope

Skipping testing is a quality risk. The PM should explain the risks and follow the change control process if the decision is to proceed without testing.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Refuse the sponsor's request outright because testing is mandatory

    Why it's wrong here

    A project manager's role involves proactive stakeholder engagement and risk management, not unilateral refusal. While testing is crucial for quality, an outright refusal without discussing the implications or exploring alternatives demonstrates a lack of collaborative problem-solving and effective communication with the project sponsor, who is a key decision-maker. The PM should inform, not dictate.

  • Explain the risks of skipping testing, including potential defects and rework, and propose alternatives such as reducing test scope

    Why this is correct

    This option exemplifies effective risk management and stakeholder communication. The project manager correctly identifies the potential negative impacts of skipping testing, such as increased post-release defects, rework costs, and reputational damage. By explaining these risks and proactively proposing alternatives like reduced test scope or phased testing, the PM demonstrates leadership, protects project quality, and facilitates an informed decision by the sponsor.

  • Skip testing but add a buffer for post-release defect fixes

    Why it's wrong here

    Unilaterally skipping a critical phase like testing and merely adding a buffer for future fixes is a reactive approach that bypasses formal risk assessment and stakeholder consultation. This action assumes the project manager has the authority to accept significant quality risks without sponsor approval, potentially leading to unforeseen costs, schedule overruns, and reputational damage far exceeding the buffer. It fails to proactively mitigate known risks.

  • Agree to skip testing to meet the deadline and document the decision

    Why it's wrong here

    Simply agreeing to skip testing, even with documentation, abdicates the project manager's responsibility to advocate for project quality and manage risks proactively. The PM must provide expert advice on the potential consequences of such a decision, including increased technical debt and stakeholder dissatisfaction, rather than passively accepting a request that could severely compromise project success. Documentation alone does not mitigate unaddressed risks.

Visual reference

Client DHCP Server 1 Discover (broadcast) 2 Offer (IP: 192.168.1.10) 3 Request (I accept) 4 Acknowledge (lease confirmed) DORA — the four-step DHCP lease process

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.