PMP Process — Managing Technical Aspects Practice Question

During a project's execution phase, the sponsor asks you to skip the user acceptance testing (UAT) phase to expedite delivery, stating that the client is eager to use the system. What should you do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Explain the risks of skipping UAT and recommend proceeding with the planned testing.

Skipping UAT poses significant quality and acceptance risks. The PM should communicate the risks to the sponsor and recommend following the quality plan. PMI emphasizes the importance of quality assurance and control processes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Skip UAT but add a note in the lessons learned about the decision.

    Why it's wrong here

    Skipping User Acceptance Testing (UAT) inherently introduces significant quality risks, potentially leading to defects, rework, and user dissatisfaction post-implementation. Merely documenting this decision in lessons learned is a reactive measure that fails to mitigate the immediate and future negative impacts on product quality and project success. A project manager's responsibility includes proactively ensuring quality and managing risks, not just recording their consequences.

  • Explain the risks of skipping UAT and recommend proceeding with the planned testing.

    Why this is correct

    This is the correct approach because a Project Manager is professionally obligated to advocate for project quality and manage identified risks. By explaining the potential consequences of bypassing UAT, such as increased defects, user dissatisfaction, and potential rework costs, the PM provides the sponsor with critical information for an informed decision. Recommending adherence to the planned testing demonstrates proactive risk management and commitment to delivering a high-quality product as per the project management plan.

  • Compromise by reducing UAT to only critical test cases.

    Why it's wrong here

    Reducing UAT to only critical test cases without a formal impact analysis and change request process is still a significant deviation from the quality management plan. While seemingly a compromise, it introduces unquantified risks to non-critical but potentially important functionalities, which could lead to project failure or significant rework later. Any modification to planned quality activities, especially those impacting scope or quality, requires a thorough risk assessment and formal approval from relevant stakeholders, not just an informal reduction.

  • Agree to skip UAT to meet the sponsor's request and expedite delivery.

    Why it's wrong here

    Agreeing to skip UAT solely to meet a sponsor's request for expedited delivery represents a significant dereliction of the Project Manager's professional responsibility. This action directly compromises the project's quality objectives, violates the established quality management plan, and exposes the project to substantial risks of defects, rework, and user rejection. A PM must prioritize the project's overall success and uphold quality standards, even when faced with pressure for speed, by communicating risks and adhering to planned processes.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.